Hyundai Heavy Industries (HHI), located in Ulsan, Korea, is WorleyParsons' subcontractor for fabrication of the Derrick Equipment Set (DES) and the Utilities/Process Module (UPM) of the topsides. The DES was transported to Bull Arm, NL in Q4 2015 where it will be integrated with the Drilling Support Module (DSM). In 2016, the UPM was transported from Korea to Bull Arm for integration with DES, DSM, LQ and other ancillary modules.
Construction Timeline

Derrick Equipment Set (DES) Construction Timeline
Q4 2013: First steel cut
2014 - 2015: Fabrication
Q4 2015: Completed DES transported to Bull Arm

Utilities/Process Module (UPM) Construction Timeline
Q3 2013: First steel cut
2014 - 2016: Fabrication
September 2016: Completed UPM arrives at Bull Arm